Morgan Stanley Says Midterm Curbs Stretch the AI Cycle
Morgan Stanley keeps $3.4 trillion of hyperscaler spending after the AI crash, treating Democratic data-center curbs as a 5 GW delay that lengthens the cycle.
Morgan Stanley left its hyperscaler spending call at $1.6 trillion for 2027 and $1.8 trillion for 2028 after the November 5 crash. That is $3.4 trillion across two years, still on the books after a midterm vote that sent the Nasdaq Composite down 5.52% in a single session.
The bank’s November 8 note, “Buy the Drop: AI Investment Opportunities Post the US Midterms,” treats the scare as a calendar move. It slides 5 GW of U.S. data-center capacity from 2028 into 2029 and argues that a slower permit line can stretch the boom, lift rents on machines already plugged in, and send work to grids that will still say yes.
The 5 Gigawatt Push Into 2029
Stephen Byrd, the Morgan Stanley equity analyst on the note, called the prior week an earthquake for anyone who had priced a straight-line build. Newly elected Democratic governors, he wrote, are unlikely to halt halls already going up, so 2027 stays put. The hit sits in 2028, in Texas and Ohio, as those governors sit down with legislators on new rules for developers.
Five gigawatts is 20% of the U.S. projects in the bank’s 2028 list and 10% of the global list. U.S. additions fall 4% in 2028, then jump 38% in 2029. Worldwide, additions still rise 9% in 2028 and 20% in 2029. The 2028 U.S. figure moves from 24.9 GW to 19.9 GW; 2029 goes from 22.7 GW to 27.6 GW. The global 2028 forecast is cut from 224 GW to 219 GW, with 2029 left at 271 GW.
THE WEEK THE AI TRADE REPRICED PERMISSION
- November 3, 2026: Democrats win the Texas, Ohio and Georgia governorships on pledges to slow or halt new data-center approvals.
- November 5, 2026: The Nasdaq Composite falls 5.52% to 24,315.00, the S&P 500 drops 4.36% to 7,353.73, and the Dow loses 1,833.06 points, or 3.44%, to 51,523.06. The Nasdaq 100 falls 6.4% and sheds $2.5 trillion. Nvidia drops 9.3%. The Philadelphia Semiconductor Index drops 12.3%. The Composite closes 10% below its October 6 high.
- November 8, 2026: Morgan Stanley publishes the 80-page note and holds the $1.6 trillion / $1.8 trillion hyperscaler totals, with a downward bias flagged only for 2028 if builds slip further.
The tape that Thursday priced a build that would not get done. The note priced a build that happens a year later. Those are different trades, and the gap is the whole argument.

Hyperscaler Budgets Stay at $1.6 Trillion
Exhibit 1 in the note keeps the headline totals and still has the large clouds “spend and build as much capacity as they can.” Google is the biggest 2027 bar at $375 billion, up from $196 billion in 2026. Amazon is $355 billion, Microsoft $269 billion, SpaceX $236 billion, Meta $225 billion, Oracle $97 billion, CoreWeave $46 billion and Nebius $37 billion. The eight-name total is $1,641 billion in 2027, up 73% from $951 billion in 2026, then $1,760 billion in 2028, up 7%.
Google, Amazon, Microsoft, Meta and Oracle sum to $1,321 billion in 2027. Meta’s 2026 bar of $144 billion sits inside Meta’s published 2026 capital budget of $135 billion to $145 billion. SpaceX is the steepest multiple in the exhibit, from $72 billion in 2026 to $236 billion in 2027, or 3.3 times.
HYPERSCALER AND AI CLOUD CAPEX IN THE NOTE
| Company | 2027 capex | Stance in the note |
|---|---|---|
| $375 billion | Overweight (Alphabet) | |
| Amazon | $355 billion | Overweight |
| Microsoft | $269 billion | Overweight |
| SpaceX | $236 billion | Named among favored spenders |
| Meta | $225 billion | Overweight |
| Oracle | $97 billion | In the eight-name total |
| CoreWeave | $46 billion | Overweight |
| Nebius | $37 billion | In the eight-name total |
Byrd’s team is Overweight Amazon, Meta, Alphabet, Microsoft, CoreWeave and Nvidia. Nvidia is in the chip column, not the cloud column, because the bank wants more AI work per watt as power stays tight. A shortage of more than 30% in powered data-center capacity is still on its books through 2028. From 2026 through 2028 it sees 116 GW of U.S. power demand tied to chip shipments and a 44 GW electrification gap, or 38% of that demand.
We believe the market’s reaction to the midterms is overdone. Over the past week, the market has undergone an earthquake event, with significant uncertainty around the impact of the midterms on the data center build-out, the trajectory of the cycle, and implications for global stocks.
Stephen Byrd, equity analyst, Morgan Stanley note of November 8, 2026
The same pages say the push-out can smooth supply and demand, improve the credit outlook, and support higher lease rates for compute that is already live. That last point was visible in the rental market before the note landed. Ornn’s index of spot rents for Nvidia B200 chips settled at $9.94 per GPU-hour on November 8, against $5.66 on August 10, a 75.6% rise in three months.
What Texas and Ohio Can Still Block
Texas is the load-bearing state in this story. It accounts for nearly 30% of U.S. data-center capacity due online in 2028. Governor-elect Gina Hinojosa beat Greg Abbott after promising to halt new approvals until the legislature writes stronger rules on power, water, taxes and local say. Abbott had already told regulators to pause some interconnection reviews for a grid and water audit. Hinojosa called that pause a pre-vote stunt and said only new law would stick.
Ohio’s Amy Acton beat Vivek Ramaswamy on a conditional freeze: developers cover 100% of utility costs, use union labor, meet environmental rules, and put jobs in old industrial towns. Georgia’s Keisha Lance Bottoms campaigned on a pause. Michigan’s Jocelyn Benson did too. New York’s Kathy Hochul won again in a state that, in July 2026, had already imposed a statewide halt on large data-center construction.
GOVERNORS WHO CAMPAGNED ON DATA CENTER BRAKES
- Texas: Gina Hinojosa wants new approvals stopped until the legislature sets protections; the state holds nearly 30% of U.S. capacity due in 2028.
- Ohio: Amy Acton wants a conditional freeze; the state already hosts more than 200 data centers, fifth among U.S. states.
- Georgia: Keisha Lance Bottoms called for a moratorium on new construction during the campaign.
- Michigan: Jocelyn Benson ran on a moratorium.
- New York: Kathy Hochul is back in a state that already paused large builds in July 2026.
Twenty-six gubernatorial candidates across 21 states backed some form of pause before election day. Voters passed 40 of 41 local ballot measures aimed at limiting or blocking projects, more than half of them in Ohio. Exit polling found 76% of respondents would oppose a new AI data center in their community.
That political map is why 5 GW can look small next to Texas alone. The bank is not moving an entire state’s 2028 slate. It is betting that halls under construction finish, that 2027 holds, and that only a slice of the 2028 queue in Texas and Ohio slips a year while new conditions are written. If those governors convert campaign pauses into hard stops on unpermitted load, the 5 GW shift is the soft reading.
Scale Wins When Permits Slow
The note’s shopping list is a quality screen dressed up as a dip. Firms that can fund their own power, shift sites to Tennessee or Louisiana, and keep model work moving without a new Texas hall are the ones it wants. Firms that need a fresh permit, a new construction loan, or a neocloud offtake are the ones it worries about. CoreWeave is still Overweight, and the 2027 bar still has $46 billion next to its name, but the same pages say new construction and neoclouds face tighter lender questions on tenant quality, a path to power, and contract protections.
That split showed up in the crash tape. CoreWeave fell about 10% on November 5 as its five-year credit default swaps widened to a record. Nebius dropped about 15%. Amazon and Alphabet each slid 2.2%, a much smaller hit for groups that can wait out a permit fight and still spend. The bank still expects more AI-related debt in 2027, led by the large clouds, and it prefers colocation paper to hyperscaler data-center asset-backed bonds because slower competing development supports sites that already throw off cash.
THREE BASKETS IN THE BUY THE DROP NOTE
- Hyperscalers: Amazon, Meta, Alphabet and Microsoft, plus Nvidia on output per watt, on the view that scale, cash and existing halls survive a slower permit line.
- Power and shells: Equinix and powered-shell names including Terawulf, Riot Platforms, Hut 8 and Applied Digital, which the bank sees as less tied to Texas rules, with Cipher, Galaxy Digital and Marathon called more exposed.
- Software and adopters: Snowflake, Datadog, Cloudflare, ServiceNow and security names such as Palo Alto Networks and CrowdStrike, on the view that value creation moves from building the plant to using it.
Median semiconductor stock in Morgan Stanley’s coverage is 53% below its peak. That is cycle-end pricing for a timing dispute. Optical vendors already talking about order books into 2029 sit in a different spot: a 2028 delay on U.S. shells does not cancel lasers that were sold against halls that still need to light up, wherever they are built.
20 Gigawatts Looking for a New Address
The bank puts 20 GW of potential spillover into Asia and EMEA if U.S. approvals lag. It also points developers toward U.S. states that still want the load, naming Tennessee and Louisiana. The IEA’s latest energy-and-AI work is the backdrop for why that hunt is physical, not financial. It found data centre electricity demand soared 17% in 2025, with AI sites rising faster still, and it has demand from data centers doubling by 2030 and power use at AI-focused sites tripling. Capex at five large technology companies passed $400 billion in 2025 and was set to rise another 75% in 2026.
In the United States, electricity use is forecast to rise close to 2% a year, more than twice the prior decade, and data centers are expected to make up about half of U.S. power demand growth through 2030. A governor who slows a 2028 hall does not retire that load. It shows up as a queue in another county, another province, or another country.
Canada is already writing the welcome packet. Alberta’s official AI data centre strategy sells power capacity, cold-climate cooling and a bring-your-own-power rule so a campus does not lean on household bills. Meta’s first Canadian campus in Sturgeon County is tagged at more than $13 billion, with a 970 MW grid connection inside an AESO interim large-load allotment of 1,200 MW that is now fully spoken for. New projects that arrive with their own generation go to the front of the line. Ontario published a data-center playbook in August 2026. British Columbia opened a competitive process with BC Hydro. Ottawa put “Responsible Data Centre Development Principles” on paper in September 2026.
The midterm vote was sold as a brake on excess U.S. building. In the bank’s geography, it is also an export order for places that will still connect a substation.
Suppliers Face a 2028 Order Hole
The ugly year in the note is 2028, and it is ugly for the people who sell into the build, not for the people who rent the finished hall. An air pocket across the tech supply chain that year can mean less pricing power, extra inventory, and a textbook downcycle even while AI demand stays strong. The bank says many valuations already bake that in. The risk it still flags is margin durability if the delay hardens into a pause, or if extra rules on labor, on-site fossil generation and emissions pile on top of the 5 GW shift.
It is also watching 2027 for a different squeeze: labs shipping much more work per watt, including Meta’s target of a tenfold jump in compute efficiency, so products scale without a matching jump in rooms. Compute constraints are old news, the note says, and data-center delays may simply keep them around longer.
WHERE EXPERTS DISAGREE
- Morgan Stanley: Totals hold, 5 GW of U.S. 2028 projects slide into 2029, suppliers can hit an order hole, and the large clouds plus selected power and software names are the buy.
- Goldman Sachs: Tighter data-center rules change where the money is spent more than whether it is spent, so the investment case still runs through 2028 without treating 2028 as an air pocket.
Both houses called the November 5 move too large for the policy math. They part on whether a slower U.S. permit line is a gift to incumbents or just a change of address for the same bill.
Software Takes the Next Leg of the Trade
The note’s last rotation is the oldest one in technology: chips, then plant, then software. Brian Nowak is Overweight Meta, Alphabet and Amazon. Adam Wood moved Microsoft to Overweight. The software sleeve (Snowflake, Datadog, Cloudflare, ServiceNow, the security names) is where the bank thinks extra return shows up once the rooms exist. Among non-tech adopters it lists firms already putting AI into earnings math, from logistics and health insurers to banks.
On power it still likes Bloom Energy, Vistra, Talen Energy, Constellation Energy and Solaris, plus the established electrical vendors over new entrants. That is the same bottleneck the IEA has been tracking: rooms are easy to announce and hard to energize, so the people who control a powered shell keep leverage when governors add paperwork.
Nvidia reports after the close on November 17, the first hard check on whether 2027 orders still match a $1.6 trillion spend year. Governors-elect take office in January 2027, which is when Texas and Ohio turn slogans into bills. Until then the market is arguing about a year on a Gantt chart, not about whether the power gets used. Morgan Stanley’s answer is that the money did not leave. It just shows up later, in fewer places, at higher rents, for the firms that can wait.
Disclaimer: This article is news reporting and analysis of a Morgan Stanley research note, public market closes and official energy and provincial policy pages. It is informational only and is not investment advice, a solicitation, or a recommendation to buy, sell or hold any security, bond or fund. Readers should consult a licensed financial adviser or other qualified professional who can weigh their objectives, time horizon, risk tolerance and tax situation before acting on any name or theme mentioned here. Ratings, capex totals, gigawatt shifts and project timelines reflect the cited research and filings as of the dates named above and can change with earnings, new state rules and revised bank models.
NEWS2 months agoClancy Juror Says the Holdout Never Cited Evidence
NEWS3 months agoThe iPhone 18 Pro Max Splits Apple’s Fall in Two
NEWS3 months agoOpenAI Calls GPT-6 Astra AGI Then Locks Its Exploits
BUSINESS3 months agoTrump Claims Hormuz Control as Oil Holds Near $96
LIFESTYLE3 months agoRussia Closes the Goethe-Institut Berlin Tried to Save
AUTO3 months agoVolkswagen’s Job Cuts Leave Four Plants Without Cars
NEWS3 months agoDyson Puts Nurovi Robots on Sale Without the UV Flagship
BUSINESS2 months agoUS Destroys Five Iranian Tankers as the Shock Hits Jordan