The Mumbai-Goa Highway’s Last Eight Kilometres Come Due
NH-66 is 99% done, yet 8 km in Maharashtra still sit unfinished after missed Parliament dates.
Around 8 km of the Mumbai-Goa highway is still unfinished, and the ministry now names April 2027 as the date the last stretches will open. MoRTH Secretary V Umashankar said 99% of NH-66 is through. The leftover work sits in five Maharashtra packages.
Union minister Nitin Gadkari, opening a 5.15 km corridor at Porvorim on 9 September 2026, said he was ashamed of the delay and would skip the highway’s inauguration.
Eight Kilometres Still Separate Two State Capitals
The 592 km NH-66 job was conceived in 2006 as a four-lane economic corridor from Panvel to Kanyakumari. The Maharashtra section runs 472 km in 13 packages. About 8 km is still pending in five of them. Goa’s 120 km from the Maharashtra border to Panaji is done, so the two capitals only meet once those 8 km are built.
Umashankar told interviewers that stalled stretches had moved in the last two years and that all pending work would be finished by April next year. A senior MoRTH official, whose ministry shares the job with the state PWD, called the corridor a showpiece example of what can go wrong in a major highway project.
THE FIVE STRETCHES STILL OPEN
| Stretch | Agency | Done | Still unfinished |
|---|---|---|---|
| Panvel to Kasu | NHAI | 97.75% | Remaining road work |
| Kasu to Indapur | NHAI | 97.75% | Remaining road work |
| Indapur to Wadpale (26.75 km) | MoRTH | 89% | Indapur and Mangaon bypasses |
| Parashuram Ghat to Arawali (34.45 km) | MoRTH | 98.5% | 1.8 km Chiplun flyover |
| Arawali to Kante (39.24 km) | MoRTH | 95% | 1.5 km of hill cutting, Sangameshwar bridge approach |
The physical leftovers are small and ugly: about 3 km of two bypasses, a 192 metre bridge, the 1.8 km Chiplun flyover, and 1.5 km of hill cutting at Kurdhunda, Kolambe, Wandri and Kante. Maharashtra’s overall cost estimate has risen about 44%, from Rs 12,532 crore to over Rs 18,100 crore, MoRTH officials said, mainly from land, site changes and extra underpasses that locals demanded.

Parliament’s Own Deadline Was September 2025
In December 2016 the government told Parliament the highway would be finished by December 2018. That date moved to 2021. Work on the first 21 km near the Goa border had started in October 2007 and was completed in 2013. Most other stretches were sanctioned in 2015-16 and awarded in 2017-18. The first Panvel-Indapur civil package had already begun on 19 December 2011.
THE DATES THAT DID NOT HOLD
- December 2016: Government tells Parliament the highway will be complete by December 2018.
- 2021: Revised finish year, after the 2018 date is dropped.
- 19 March 2025: Nitin Gadkari, in a Rajya Sabha reply, puts the original sanctioned cost at Rs 14,106 crore, the revised cost at Rs 19,469 crore, and the leftover length at 24 km, targeted for September 2025.
- 9 September 2026: Gadkari, at Porvorim, says the job is about 93% to 94% done, he is ashamed, and he will not attend the opening.
- November 2026: Umashankar says 99% is through and names April 2027 for the rest. The 1.8 km Chiplun flyover, listed for commercial opening this month, is still shut.
The March 2025 snapshot was on a Panvel-Panaji measure of about 500 km, with four-lane work then complete on 463 km. Gadkari’s own reply remaining 24 km by September 2025 blamed land, other pre-construction work and cash-flow trouble at some contractors, and said those issues had been substantially resolved with the state. September 2025 came and went. The new ministry date is April 2027. The revised Rs 19,469 crore figure sits on a slightly different length than the Maharashtra-only Rs 18,100 crore-plus estimate; both are official, and both are up.
The Land Rule the Awards Did Not Wait For
Agencies that acquire land under the National Highways Act have been told for years to get most of the right of way in hand before a contractor is appointed. A 2014 EPC guideline already asked for 90% of the land before the agreement was signed. The 2020 model concession agreement for BOT toll jobs told NHAI to hand over 90% of vacant land before work started, with a fine if it did not.
The Mumbai-Goa packages awarded in 2017-18 still ran into forest files, utility shifting, court cases and protests. MoRTH now says environment and forest clearances must be complete before a tender is invited, and at least 90% of land acquisition should be done before a project is awarded. That is the rule the 2017-18 awards did not wait for.
On 6 May 2025 the ministry put the tighter version on paper, for tenders issued from 1 June 2025. NHAI’s own pre-construction note still starts from the same point: handing over encumbrance-free land to the contractor is the first requirement, and it includes land, environment clearances and utility shifting.
WHAT THE MAY 2025 CIRCULAR NOW DEMANDS
- Environment and wildlife: Clearances, plus railway drawings and utility-shifting estimates, must be in place before bids are received.
- Forest: Clearance must be obtained before the letter of award is issued.
- Land notices: A Section 3D declaration for over 90% of the required land before bids are invited, and Section 3G compensation for more than 90% before the letter of award.
- Possession: Over 90% of the land in hand on or before work starts on the ground, with 100% of the approach land beside a standalone bridge, road-over-bridge or tunnel before the letter of award.
The circular is an admission written as a timetable. It will not rebuild the five packages already awarded, terminated and awarded again on NH-66. Officials have also begun terminating slow contractors and capping costs on ministry jobs given to state PWDs.
The Firms That Took Over After the Terminations
The 84.6 km Panvel-Indapur pair was first a BOT job for a consortium led by listed Supreme Infrastructure India, with its BOT arm, City Universe (a subsidiary of China State Construction Engineering (Hong Kong)) and Mahavir Roads. They finished 36 km of the 84 km by 2017. Supreme then defaulted on bank loans and appeared on the Reserve Bank’s top-100 defaulters list in 2019. The contract was terminated in 2021. A March 2025 NCLT restructuring cut the group’s debt from Rs 2,200 crore to Rs 464 crore. The BOT arm later went into liquidation. The original Rs 943 crore cost is in arbitration.
Panvel to Kasu went in March 2023 to J M Mhatre Infra, a Panvel firm whose politician-businessman owner, J M Mhatre, is under an Enforcement Directorate probe over alleged forest-land fraud. He held over 17% of the company, with the rest in the family, and reported a profit of Rs 5.08 crore in FY 2024-25. He was with the Peasants and Workers Party and joined the BJP in 2025. Kasu to Indapur went in November 2022 to Indore’s Kalyan Toll Infrastructure, which reported a profit of Rs 141 crore in FY 2024-25. Neither firm answered questions. Officials said land and utilities on this pair had been sorted and that Supreme’s problem was money.
Indapur to Wadpale, 26.75 km, went in December 2017 to a joint venture of Udaipur’s Chetak Enterprises and Lucknow’s APCO Infratech, due in 2021. Registrar of Companies filings show Congress leader Udai Lal Anjana, Rajasthan’s former co-operatives minister from 2018 to 2023, holds over 40% of Chetak and close to 87% with his family. Chetak made a profit of Rs 32.46 crore in FY25. APCO, run by Uttar Pradesh industrialist Anil Kumar Singh with over 37%, made a profit of Rs 738 crore in FY25. Forest clearances, utilities, land and other pre-construction work dragged. The ministry terminated the joint venture in June 2025. The leftover 10.6 km of the Indapur and Mangaon bypasses went in October 2025 to Jaipur’s LNA Infraprojects. Anjana could not be reached. His brother Manohar Lal Anjana, who holds 26.66%, said he knew they had two sections and was not aware of the status. APCO did not respond.
The same Chetak firm is still on the next package. Parashuram Ghat to Arawali, 34.45 km, was awarded in December 2017 to Chetak with Thane’s Eagle Infra India, run by the Rupchandani family, with Udhav Rupchandani as CEO. Eagle, a Rs 929 crore company, made a profit of Rs 253 crore in FY25. Land fights and court cases left the 1.8 km Chiplun flyover unfinished. That package’s cost rose from Rs 983 crore to Rs 2,226 crore, a 126% jump, the steepest on the unfinished list. Eagle did not respond. Chetak was terminated for delay on one NH-66 job and left in place on the next.
Arawali to Kante, 39.24 km, went in November 2017 to MEP Infrastructure Developers and San Jose India, a Spanish-group subsidiary. MEP, controlled by Mumbai’s Mhaiskar family with Jayant D Mhaiskar as chairman, defaulted on a Rs 128 crore loan from Intec Capital. The NCLT opened insolvency proceedings in March 2024 and the ministry retendered. The 2024 award went to Hazoor Infra Projects, an October 2023 special-purpose vehicle under listed Hazoor Multi Projects. Chairman and managing director Radheshyam Mopalwar is a former vice chairman and MD of the Maharashtra State Road Development Corporation and ran the Samruddhi Expressway. Hazoor Infra reported a profit of about Rs 12 crore in FY25. Cost on this stretch rose from Rs 1,102 crore to Rs 1,443 crore, up 31%. A Hazoor executive said the rest would be done in a month, and that blasting in populated areas plus a railway section, a temple and a crematorium had held the job. Mhaiskar said the project had not been with MEP for five years and that the company was still under CIRP.
Chiplun’s Flyover Missed Its November Opening
Progress reports had the Chiplun flyover opening for commercial traffic in November 2026. It has not. Engineers on the stretch are now talking of a year-end finish, with paving and the short joining roads still under way. Gadkari had already taken the political heat in Goa two months earlier.
I had announced that I would not come for the inauguration of the Mumbai-Goa highway because I felt ashamed that it had been delayed so much.
Nitin Gadkari, Union minister of road transport and highways, at Porvorim on 9 September 2026
He also said the contractors had failed, that the delay was unfortunate, and that he wanted his department to hold a record for blacklisting contractors and suspending officials in a single year. He said he would land in Mumbai in October and drive to Goa to see whether the journey had actually become convenient. The leftover 8 km was still listed as unfinished in November.
Chiplun is also where the agencies point at each other. When drone video of potholes near Vasishthi Bridge spread in August 2025, NHAI said that bit of the Mumbai-Goa highway is maintained by the state PWD’s national highway division, not by NHAI.
NHAI would like to inform that the Mumbai-Goa National Highway in Chiplun near Vasishthi Bridge does not fall under NHAI’s jurisdiction and is maintained by the NH Division of PWD under the state government.
— NHAI (@NHAI_Official) August 22, 2025
Panvel to Indapur is an NHAI job. Indapur south is MoRTH work through the state PWD. Drivers already treat the unfinished Chiplun flyover as a failure that does not even have a land excuse, and they use this highway as the warning example when other roads start to slip. The jurisdiction reply reads as evasion on a route that is supposed to be one corridor.
What the Remaining Work Still Has to Clear
The government’s investment listing for the Indapur and Mangaon bypass balance work puts that 10.6 km job on a 7 October 2025 start and an 8 April 2027 finish, in line with Umashankar’s April 2027 date for every leftover stretch. Konkan Railway ran a mega-block from 26 October to 4 November 2026 so girders could be lifted over the electrified tracks. By early November the Mangaon girders were in place. The bypass was still not open.
WHAT IS STILL IN THE WAY
- Two bypasses: Indapur and Mangaon, about 3 km plus the longer 10.6 km balance, crossing the Konkan Railway on new flyovers.
- Chiplun flyover: 1.8 km of deck, still closed after a listed November 2026 commercial opening.
- Hill cuts: 1.5 km at four places on Arawali-Kante, where blasting is boxed in by houses.
- Local land: a railway parcel, a temple and a crematorium on the Hazoor stretch, plus older court cases on the Chiplun package.
The last 8 km is the part that was never shovel-ready when the 2017-18 letters of award went out. Cash-flow failures at Supreme and MEP made it worse, and politically connected firms sat on packages that then had to be pulled and retendered. The May 2025 circular will govern the next highway, not this one. April 2027 is now the date on the leftover work. It is also the latest in a line that began with December 2018.
NEWS2 months agoClancy Juror Says the Holdout Never Cited Evidence
NEWS3 months agoThe iPhone 18 Pro Max Splits Apple’s Fall in Two
NEWS3 months agoOpenAI Calls GPT-6 Astra AGI Then Locks Its Exploits
BUSINESS3 months agoTrump Claims Hormuz Control as Oil Holds Near $96
LIFESTYLE3 months agoRussia Closes the Goethe-Institut Berlin Tried to Save
AUTO3 months agoVolkswagen’s Job Cuts Leave Four Plants Without Cars
NEWS3 months agoDyson Puts Nurovi Robots on Sale Without the UV Flagship
BUSINESS2 months agoUS Destroys Five Iranian Tankers as the Shock Hits Jordan