Gujarat Will Run India’s First Bullet Train Before Mumbai
India will open its first bullet train in 2027 on Gujarat’s Surat-Vapi stretch, while Mumbai’s undersea tunnel and the original Japanese trainsets remain unfinished.
India’s first bullet train will enter service in 2027 on the Surat-Vapi stretch in Gujarat, Railway Minister Ashwini Vaishnaw said, with Mumbai still waiting on an undersea tunnel. The full Mumbai-Ahmedabad corridor is 508 km. The first tickets will be sold on a Gujarat hop while the 21 km Maharashtra tunnel, including 7 km under Thane Creek, is still being bored.
Vaishnaw wrote that the first high-speed service starts in the last quarter of 2027, and that the rest of the line to Mumbai will open in phases. The trains on that first run will be Indian-built B28 sets, designed for 280 kmph and billed to run at 250 kmph at first, below the corridor’s 320 km/h operating speed.
Surat to Vapi Opens Before Mumbai Does
The National High Speed Rail Corporation Limited lists eight of the 12 stations sit in Gujarat, with four in Maharashtra. Gujarat holds 348 km of the alignment, Dadra and Nagar Haveli 4 km, and Maharashtra 156 km. The 2027 opening sits entirely on the Gujarat side: Surat, Bilimora and Vapi. Boisar, Virar, Thane and the underground Mumbai terminal at Bandra Kurla Complex are not on that first timetable.
Railways planning papers put the Surat-Vapi passenger section at about 97 km. That is a commissioning slice of a line sold in 2017 as a Mumbai-Ahmedabad business corridor. NHSRCL’s own figures say a limited-stop run over the full 508 km, calling at Surat, Vadodara and Ahmedabad, should take 2 hours 7 minutes. An all-stops run is put at 2 hours 58 minutes. A Surat-Vapi shuttle does not deliver that journey.
THE CORRIDOR SPLIT
| Item | Gujarat and DNH | Maharashtra |
|---|---|---|
| Alignment | 348 km plus 4 km | 156 km |
| Stations | 8 (Sabarmati, Ahmedabad, Anand, Vadodara, Bharuch, Surat, Bilimora, Vapi) | 4 (Boisar, Virar, Thane, Mumbai) |
| 2027 passenger start | Surat, Bilimora, Vapi | None |
| Hard remaining civil work | Finishing, power, trials | 21 km tunnel, 7 km of it undersea |
About 465 km of the 508 km, over 90 percent, is planned on viaduct. That raised work is furthest along in Gujarat, which is why a train can be timetabled there while Mumbai is still a shaft and a cutterhead.

Why the First Ride Stops in Gujarat
Prime Minister Narendra Modi and Japan’s Shinzo Abe laid the foundation stone in Ahmedabad on September 14, 2017. Japan was to fund most of a project then costed at Rs 1,08,000 crore, with a soft loan of Rs 88,000 crore at 0.1 percent, repaid over 50 years after a 15-year grace period. Political talk at the launch pointed to 2022. JICA’s loan paper said the facilities would be put the line into service in December 2023.
Vaishnaw’s account of the gap is blunt. The project could not start in Maharashtra for close to two and a half years because state permissions and land did not come. Covid then took two more years. Full construction, he wrote, began in earnest in 2021.
So, when critics ask, ‘where is the bullet train?’, the honest answer is: serious construction is just five years old. And look at what five years have built!
Ashwini Vaishnaw, Union Railway Minister, on Substack
NHSRCL’s FAQ puts land for the alignment at 1,390 hectares, with 430 hectares in Maharashtra and 960 hectares in Gujarat and Dadra and Nagar Haveli. Gujarat let civil contracts for its stretch years before the Maharashtra tunnel machines turned. The first ride follows that land clock, not the 2017 map that put Mumbai at one end and Ahmedabad at the other.
FROM STONE-LAYING TO A GUJARAT STUB
- September 14, 2017: Modi and Abe lay the foundation stone in Ahmedabad.
- September 28, 2018: JICA signs the first construction loan; its paper dates full service to December 2023.
- 2021: Vaishnaw says full construction begins after the Maharashtra stall and Covid.
- July 2026: Two tunnel boring machines launch from Vikhroli and Sawli.
- September 2026: Pier work 456 km, viaduct 371 km, as Vaishnaw tallied it.
- November 20, 2026: NHSRCL schedules live overhead wires on Surat-Bilimora.
- Mid-2027: Track trials of the B28 trainset are expected.
- Last quarter of 2027: First passenger service, Surat to Vapi.
JICA’s demand study, written for a 2023 opening, put about 30,000 passengers a day at Mumbai station and about 21,000 a day at Ahmedabad. The loan case was the two termini. Surat-Vapi was never the product on that paper.
Five Kilometres of a 21 km Tunnel
In Maharashtra the line leaves Bandra Kurla Complex in a 21 km tunnel, and 7 km of it passes under Thane Creek. Vaishnaw called it India’s first undersea rail tunnel. As of September 2026, 5 km of that 21 km had been dug by the mountain tunnelling method. The long bored drive, including the creek, is the job of two machines launched only in July 2026.
THE MACHINES UNDER THANE CREEK
- Launch points: Vikhroli and Sawli, July 2026.
- Cutterhead: 13.6 metres across, as tall as a 4-storey building, Vaishnaw wrote.
- Mass: Each over 3,000 tonnes, which he compared to roughly 500 Asian elephants.
- Length: 96 metres, nearly five cricket pitches laid end to end.
Until those drives finish, there is no high-speed path into Mumbai. Thane, Virar and Boisar wait on the same underground and approach works. Gujarat can finish viaducts, pour J-slab track and hang wires. Maharashtra still has to mine a city and a creek.
Vaishnaw quoted Masafumi Shukuri, chairman of the International High-Speed Rail Association, saying Japan could not have done the elevated work at this speed. The compliment attaches to the viaduct. It does not move the tunnel.
ICF and BEML Are Filling a Japanese Gap
The 2017 pitch was Japanese Shinkansen trains on a Japanese-standard line. The first sets now due on Surat-Vapi are the B28, designed by the Integral Coach Factory and built by BEML at its Aditya plant in Bengaluru. Vaishnaw wrote that the first body frame is complete and in structural testing, with track trials expected by mid-2027, and that a faster B35 designed for 350 kmph is the next step.
The Ministry of Railways has been direct about why the B28 exists. “We face certain challenges in obtaining the rolling stock from Japan. We are manufacturing the B28 right here in India,” the ministry said. “This signifies that it has been designed to operate at a speed of 280 kmph. In the initial phase, however, it will run at 250 kmph.”
The Railways’ own description of the set is an eight-car train about 202 metres long, four motor cars and four trailers, with a passenger capacity of 557. Two of those eight-car sets can be coupled later. The corridor around them is designed for 350 kmph and an operating speed of 320 km/h. The first Indian “bullet train” will therefore open below the speed printed on the alignment.
Fixed kit is being made here too. Vaishnaw wrote that major transformers for the high-speed electrification system, the cross arms on the masts, and the ground, protection and feeder wires are all being manufactured in India, and that Japanese J-slab ballastless track is being cast in Indian yards. ICF and BEML pick up the train order Japan did not fill on the original clock. Gujarat picks up the first service. Mumbai picks up the wait.
NHSRCL Puts the Revised Cost at Rs 2,02,797 Crore
An NHSRCL reply under the Right to Information Act, covering figures to March 2026, put spending so far at Rs 92,761 crore and the revised estimate at Rs 2,02,797 crore. The 2017 launch figure was Rs 1,08,000 crore. That is nearly double (2,02,797 divided by 1,08,000 is 1.88).
THE 2017 PLAN AND THE 2026 BOARD
| Item | 2017 plan | Now |
|---|---|---|
| First service | December 2023 in the JICA paper; 2022 in political remarks | Last quarter of 2027, Surat to Vapi |
| Project cost | Rs 1,08,000 crore | Rs 2,02,797 crore (NHSRCL RTI) |
| First trains | Japanese Shinkansen stock | B28, 250 kmph at first |
| What opens first | The Mumbai-Ahmedabad corridor as one system | A Gujarat section; Mumbai in later phases |
Japan still sits on the civil standard, the J-slab, the training pipeline and the cheap yen credit. What it does not have, on present plans, is the first passenger train into Mumbai, or the first rake in commercial service. Those go to a Gujarat stub and a Bengaluru shop floor.
The Surat-Bilimora Wires Carry 25,000 Volts
The piece of railway that actually goes live first is shorter than Surat-Vapi. A Press Information Bureau note dated November 18, 2026 said NHSRCL would energise the 50 km Surat-Bilimora section on November 20, 2026. That stretch is both up and down lines on the elevated alignment. It is the power-on test for a passenger section that Vaishnaw has since framed as Surat to Vapi.
The Mumbai–Ahmedabad Bullet Train corridor is set to power up its first section i.e. Surat-Bilimora on 20 November 2026. pic.twitter.com/j78qudQmXf
— NHSRCL (@nhsrcl) November 18, 2026
The corridor uses a 2 x 25 kV overhead traction system, new to Indian railways at these speeds. NHSRCL’s electrification brief lists 14 traction substations along the corridor, nine in Gujarat and five in Maharashtra, plus nearly 22,000 steel masts and more than 25,700 cantilever assemblies across 1,125 track kilometres including depots. As of September 2026, Vaishnaw put 9,300 of those masts on 206 km of viaduct, with 6 lakh noise barriers along 299 km.
SEPTEMBER 2026 TALLY
- Piers: 456 km of pier work complete on the 508 km line.
- Viaduct: 371 km of viaduct built, using 40-metre, 970-tonne full-span girders.
- Stations: Civil work done at eight of 12; architectural finishing under way.
- Depots: Work in progress at Sabarmati, Surat and Thane.
Four mountain tunnels are already excavated. Live wires on 50 km in Gujarat do not equal a certified passenger railway. Trials, signalling, the B28 and safety clearances still sit between those masts and a public timetable.
Mumbai’s Station Is 32 Metres Underground
The only underground station on the corridor is at Bandra Kurla Complex. Vaishnaw wrote that the pit goes about 32 metres below ground, with three levels and six platforms, each over 400 metres long, built for full-length high-speed sets. It is a station in a working business district, with towers, roads and metro lines around the hole. It is also useless to a passenger until the tunnel reaches it.
Surat’s elevated station, by contrast, is far enough along that Vaishnaw could describe a facade inspired by diamond facets and say that when the first service starts from Surat in 2027, the city will be where India’s high-speed journey began. That sentence is the geography of the delay, stated as a civic boast. Gujarat had land, viaduct and a depot. Maharashtra had a creek, a court fight over Vikhroli land, and machines that started turning in July 2026.
A first section of about 97 km at 250 kmph is a trial railway that happens to carry passengers. It does not stitch Mumbai, Thane, Vapi, Surat, Vadodara, Anand and Ahmedabad into one labour market, which was the case Vaishnaw still makes when he writes about the finished corridor. The people who will be able to board in 2027 are in Surat, Bilimora and Vapi. The people the 2017 loan paper counted in the tens of thousands a day are still looking at a 32-metre pit and a cutterhead under Thane Creek.
NEWS2 months agoClancy Juror Says the Holdout Never Cited Evidence
NEWS3 months agoThe iPhone 18 Pro Max Splits Apple’s Fall in Two
NEWS3 months agoOpenAI Calls GPT-6 Astra AGI Then Locks Its Exploits
BUSINESS3 months agoTrump Claims Hormuz Control as Oil Holds Near $96
LIFESTYLE3 months agoRussia Closes the Goethe-Institut Berlin Tried to Save
AUTO3 months agoVolkswagen’s Job Cuts Leave Four Plants Without Cars
NEWS3 months agoDyson Puts Nurovi Robots on Sale Without the UV Flagship
BUSINESS3 months agoUS Destroys Five Iranian Tankers as the Shock Hits Jordan